«Diamant» in the Making
Work on our new «Diamant» production facility is continuing. A key feature of the building is the adaptive Solskin solar facade, which, together with the roof-mounted solar panels, will in future help to meet part of the site’s energy requirements.
Energy
District heating 800 kW, utilisation of process waste heat
Photovoltaics
Roof: 200 kWp, approx. 170 MWh/a, electricity for around 35 households
Adaptive solar facade: 1’250m², 115 kWp, approx. 100 MWh/a, electricity for around 20 households
Modules: 3'488 Solskin modules
Planned commissioning: October 2026
100 percent of the energy generated in future will be used for the company’s own consumption.

You can track the progress live on our partners webcam.